Teknis

How Long Does It Take to Build a Padel Court? A Stage-by-Stage Timeline

The first question almost every client asks is "how long until the court can be used?" The honest answer depends on the ground, the weather and how quickly decisions get made. Here is a realistic schedule for one FIP-standard court in Medan and North Sumatra, stage by stage.

Timeline for one court (indoor or roofed outdoor)

StageDurationNotes
Survey, design, working drawings1–2 weeksGround check, light orientation, drainage, 3-phase power.
Earthworks & foundation slab2–3 weeksCompaction, reinforced concrete slab with 0.5% drainage fall.
Concrete curing3–4 weeksCannot be rushed; turf laid on green concrete ripples later.
Steel structure & 12 mm tempered glass2–3 weeksImported glass panels need 4–8 weeks lead time — ordered at design stage.
Synthetic turf, silica sand, lines1 weekSand infilled in stages to keep it level.
LED lighting, roof, nets, finishing1–2 weeksLux test 300–500 for commercial courts.

Total: 10–14 weeks for a single court, 14–18 weeks for a 3–4 court club with a lobby. Medan's rainy season (October–January) adds 2–3 weeks to earthworks and curing.

What slows projects down most

How to shorten the schedule

  1. Fix glass, turf and lighting specifications in week one.
  2. Apply for the PLN capacity upgrade alongside earthworks.
  3. Build the roof in parallel with concrete curing.
  4. Use one contractor for civil, steel and court works — vendor coordination is the most common cause of delay.

See also the padel court construction cost and technical standards.

FAQ

Can a padel court be finished in 2 months?

For one outdoor court with glass in stock and firm ground, yes; 10–14 weeks is the safe figure.

Does the rainy season stop the project?

It does not stop it, but earthworks and curing slow by 2–3 weeks; roof and steel can continue.

When should we start to open for the year-end holidays?

Start earthworks by August at the latest and order glass in July.